MW-638 is a 38 mm HDPE turf cell and gravel paving grid for light-vehicle routes, pedestrian areas, verges and permeable landscape surfaces. The connected cellular modules hold gravel or planting media in place and reduce surface rutting when installed over a properly designed base. Its lower profile and lighter weight distinguish it from the 50 mm MW-650 model intended for heavier vehicle applications.

Suitable Uses for MW-638

  • Light-vehicle gravel roads and driveways
  • Pedestrian paths and landscaped verges
  • Overflow parking with controlled traffic
  • Garden routes, golf buggy paths and recreation areas
  • Grass or gravel surfaces requiring cellular reinforcement

The grid supports a permeable finish, but infiltration performance depends on the whole pavement structure and the permeability of the subgrade. Where soils drain slowly, the designer may need underdrains or a controlled outlet.

MW-638 Technical Data

PropertyValue
Item No.MW-638
Size410 × 430 × 38 mm
MaterialHDPE
Weight4.05 kg/m²
Declared pressure strength1,584 kN/m² (160 t/m²)
Working temperature−40°C to 90°C
DurabilityAt least 8 years in neutral ground, pH 4–9 (original data)
Packing8 pcs = 2 m²/bundle
Indicative loading940 m²/20 ft; 1,910 m²/40 ft; 2,160 m²/40 HQ

MW-638 turf cell gravel paving grid

Base Preparation and Installation

Excavate to the design formation, compact the subgrade and install the specified separation geotextile. Place and compact the graded aggregate base, then level the bedding layer. Connect the MW-638 modules, cut neatly at edges and fill the cells with selected gravel or planting media. The base thickness must be calculated for the soil condition, drainage, frost and traffic; a generic detail cannot replace project engineering.

subsoil layers for MW-638 gravel paving grid

MW-638 turf cell grid installation procedure
Typical grass-grid installation sequence

Project References

turf cell grid parking project MW-638 grass grid after installation permeable gravel paving grid area

Project Enquiry

Send the area, expected vehicle type, subgrade information, chosen infill and destination to our project team. We can calculate module quantity and packing; the pavement engineer should approve the final base design.

Get in Touch

We'd love to hear from you. Please fill out the form below.

Please enable JavaScript in your browser to complete this form.