Modular Roof Runoff Detention and Storage Tank

This modular roof runoff detention and storage tank receives rainwater from building roofs and temporarily holds it underground before controlled discharge. Where water-quality treatment and local rules allow, part of the stored volume may also support approved non-potable reuse.

PP module for roof runoff detention

System role and suitable projects

The page focuses on detention performance for roof runoff, distinguishing it from a reuse-only tank. The system must be sized for the design storm, permitted discharge rate, available footprint and any required reuse reserve.

  • Commercial roof runoff detention
  • Residential development flow control
  • Combined attenuation and limited non-potable reuse
  • Sites with restricted drainage discharge rates

Modular roof water storage tank detail

Module specifications

The following values are the legacy product specifications for this module. Structural capacity, cover depth, traffic loading and applicable test requirements must be checked for the actual project design.

TypeRainwater Collecting Modular
Place of OriginFujian China(Mainland)
Brand NameLEIYUAN
Material:PP
Color:Black
Dimension680 L*410 W*450Hmm
Total Volume:0.125m3
Tank per m38
Weight:8kg/module
Working Temperature:From -30℃ to +120 ℃
Pressure Strength:25tons/sqm
HS Code:3925900
Certificate:ISO9001:2008

How the modular tank works

Roof drainage is routed through suitable debris and sediment control into the modular tank. An engineered outlet regulates discharge, while overflow protects the system during larger events; pumps and additional treatment are added only when reuse is included.

Roof runoff tank component view

Installation planning

  1. Confirm runoff volume, design storm, inflow and discharge requirements.
  2. Check excavation, groundwater, soil bearing conditions and required cover depth.
  3. Prepare a level base and assemble modules according to the approved layout.
  4. Wrap the structure with the specified geotextile and/or waterproof membrane.
  5. Connect inlet, outlet, ventilation, inspection and overflow components.
  6. Backfill in controlled layers and commission the system before operation.

Roof detention tank installation guide

Roof stormwater storage project

Packing and project support

Detail:SizePacking
680x410mm8pcs/bundle
450x410mm10pcs/bundle
Shipping:90 Cubic Meter for 1X20′ GP(By bundle)

Module quantities and container loading should be confirmed from the final tank geometry and current packing plan. Leiyuan can review project volume, module layout and shipping requirements for professional buyers.

Roof runoff module packing

Leiyuan roof water tank module factory

Information required for a quotation

Send the project location, required storage volume, application, installation depth, surface load, groundwater level, drawings and delivery destination. This allows the module and system build-up to be checked before quotation.